Project Lifecycle

1. Proposed​

Capture the problem, intended outcome, sponsor, initial lead, constraints, dependencies, and rough effort.

2. Approved​

Record the steering decision, committed scope, success measures, team, budget or capacity boundary, risks, and target dates.

3. Active​

Maintain current status, decisions, risks, milestones, and material scope changes.

4. Paused​

State the reason, preservation requirements, restart conditions, accountable owner, and review date.

5. Shutting down​

Stop new commitments, inventory deliverables and dependencies, transfer or archive ownership, revoke project-specific access, and communicate impact.

6. Closed​

Record the shutdown decision, final outcome against success measures, retained artifacts, unresolved obligations, lessons learned, and closure date.